Torrance Centennial Plaza Construction, FEAP-739

Engineering Manager: Elizabeth Overstreet, P.E.
Project Engineer: Lea Reis

Description:

The Torrance Centennial Plaza Construction Project, FEAP-739 provides for the construction of the 100 year commemorative plaza at El Prado Park with time capsule. Construction will include hardscape, seating, landscaping, irrigation, signage and lighting. Improvements are to be completed by end of August, in time for the opening ceremonies of the City of Torrance Centennial Celebration.

NOW ADVERTISED FOR BIDS.  REFER TO THE "NOTICE INVITING BIDS" BELOW FOR MORE INFORMATION

NOTICE INVITING BIDS

TORRANCE CENTENNIAL PLAZA PLANS

CENTENNIAL PLAZA SPECIFICATIONS

ADDENDUM #1

ADDENDUM #2

 

CLARIFICATION/REQUEST FOR INFORMATION:

THERE IS NO MANDATORY WALK THROUGH FOR THIS PROJECT

SHEET 9, DETAIL 3/C2 SHOWS A FLAG POLE. THIS IS NOT A REQUIREMENT OF THE PROJECT. ONLY THE FLAG POLE SLEEVES AND FOUNDATIONS ARE TO BE INSTALLED, AS SHOWN, TO ACCOMODATE THE POLES.

TIME CAPSULE DIMENSIONS ARE 16" X 16" X 30" . TIME CAPSULE WILL BE PROVIDED BY THE CITY TO FIT INTO THE VAULT. SEE SHEET 3 DETAIL 5.

 

BID RESULTS